Our tenth annual index is here, offering our broadest view of the global data center market to date. Covering 62 markets, with 12 new additions this year, it draws on data from over 500 live or recent projects and a survey of 401 industry leaders. The index provides valuable insights into the trends and challenges shaping data center development in the United States and around the world.
U.S. data center development in a changing global market
The global data center sector has moved from a niche part of commercial real estate to a major driver of construction activity and the wider economy. Artificial intelligence is accelerating demand for computing power across the United States and globally, reshaping how projects get built.
Our Data center construction cost index 2026–27 provides indicative construction costs per watt and index scores for 62 markets, including the United States, alongside insights into the trends, risks and new strategies shaping the sector. It's built on ten years of market data and a survey of over 400 leaders across the industry, so you can plan your next project with a clearer, data-led view of what lies ahead.
Key findings from this year’s research
U.S. construction costs and the AI premium
In the United States, data centers built to handle AI workloads cost around 10% more than traditional facilities. Higher rack density, liquid cooling requirements, and accelerated delivery schedules are the primary drivers. The most advanced AI-specific facilities are seeing cost-per-watt construction rates of between US$14.00 and US$16.00—significantly above the US$12.08 country average.
Costs are stabilizing, but structurally higher
52% of survey respondents experienced cost inflation of between 6 and 15% in 2026. Our Index shows North American and European markets seeing the sharpest rises, with average cost per watt up 13% year on year.
Skilled labor shortages are a strategic risk
81% of respondents say skilled labor in their region is constrained. Mechanical, electrical, and plumbing (MEP) trades remain the most sought-after. As more projects incorporate on-site power generation, demand for electrical specialists is growing further. For U.S. data center developers, these workforce pressures highlight the importance of early resource planning and securing specialized expertise to support project delivery.
The most expensive data center markets
North America has 13 markets represented in the index, alongside 17 European markets. Together, these regions make up almost half the total table, reflecting continued high costs in mature regions. Japan leads the index for the fourth consecutive year, with Tokyo topping the table at US$18.28 per watt, followed by Osaka at US$17.15 per watt and Zurich at US$15.93 per watt.
Scale doesn't guarantee lower costs
Larger projects are no longer a reliable route to drive economies of scale. Labor and equipment constraints, greater design flexibility and schedule uncertainty are driving up prices through higher labor costs, risk premiums and extended schedules.
Future outlook
Confidence in the sector remains strong. 74% are confident the industry is resilient to economic downturn.
AI is driving an unprecedented pipeline of demand, with 39% of respondents working primarily on AI-ready facilities over the past 12 months and 53% anticipating AI-dominant workloads in the year ahead.
Governments are becoming active participants in the sector, not just regulators, with numerous examples globally of multi-billion sovereign investment programs. Many governments are also playing a more active role incentivizing and streamlining data center delivery, reflecting the sector’s importance for wider economic growth.
In the United States, future data center development will also be shaped by power availability, regulatory developments and workforce costs. The index highlights Texas grid capacity, potential changes to federal energy equipment regulations, and mechanical, electrical and plumbing labor inflation as key factors to monitor as the sector continues to expand.
The organizations that lead through the next decade will be those that secure critical resources early, build closer partnerships with suppliers, and adapt quickly as market, regulatory and technology demands evolve.
The sector’s challenges are increasingly interconnected and must be met with integrated solutions.
What's inside the index?
- A full ranking of 62 markets, with cost per watt and index scores based on a typical 60MW design
- Analysis of 12 new markets added to the index this year, including Hong Kong, Rio de Janeiro and Barcelona
- A standalone chapter on the AI premium, with a spotlight on construction costs in the United States
- Insight into skilled labor shortages, the shift to liquid cooling and the rise of alternative delivery models
- A look at the role of government, data sovereignty and the long-term outlook for the sector
Whether you're planning a single data center or managing a global portfolio, the index gives you the benchmarks and insight you need to plan capital, manage risk and deliver with confidence.
Explore our flagship, data-led market intelligence reports
Get our latest insights direct to your inbox
Sign up for our newsletter - trends, market intelligence and expert perspectives.
Get our latest insights direct to your inbox
Sign up for our newsletter - trends, market intelligence and expert perspectives.