Eskom - Kimberley strengthening scheme

Boosting capacity across the electricity value chain

To support the Eskom in the construction of 420km of new 400kV transmission lines in the Kimberley area as well as the deviation of 275kV transmission lines, we provided cost management assistance throughout the lifecycle of these projects.

Key information

Completion date: Ongoing

We have developed a close working relationship with the client team, facilitating the transfer of knowledge and skill and adding to the success of the project.

Our contribution

Turner & Townsend provided cost management services to Eskom, including:

Making the difference

Apart from the services provided above, Turner & Townsend is also transferring skills to Eskom, with the teams working closely together. The 275kV Deviation at the sub-station has been successfully completed, meeting both the programme and budget requirements. 

  • 95% electricity used in South Africa is generated by Eskom
  • 45% electricity used in Africa is generated by Eskom